The Government of Alberta has issued a request for proposals for the first of eight sections of work on Highway 3 between Saskatchewan and British Columbia.
The eight phases of this project include:
- Phase 1: 46 kilometres – A request for proposals has been issued to the shortlisted design build proponents to twin Highway 3 between Taber and Burdett. Construction is expected to start in 2023.
- Phase 2: 10 kilometres – Highway 3X/Coleman Bypass. Functional planning studies have been completed and detailed engineering design will begin in spring 2023.
- Phase 3: 15 kilometres – East of Seven Persons to Medicine Hat. Functional planning studies have been completed and detailed engineering design will begin in spring 2023.
- Phase 4: 47 kilometres – Blairmore to east of Highway 6 at Pincher Creek. Functional planning studies have been completed and detailed engineering design will begin in 2023.
- Phase 5: 28 kilometres – East of Bow Island to east of Seven Persons. Functional planning studies have been completed and detailed engineering design will begin in summer 2023.
- Phase 6: 23 kilometres – East of Burdett to east of Bow Island. A functional planning study has been completed and the province will continue to consult with the Town of Bow Island and other stakeholders in order to finalize the alignment.
- Phase 7: 38 kilometres – Pincher Creek to west of Fort Macleod. A functional planning study through Piikani Nation is underway and will continue for some time.
- Phase 8: Eight kilometres – Alberta-B.C. border to Highway 3X. Continued engagement with B.C. is necessary to consider alignment with improvements being planned through the B.C. portion.
“Alberta is focused on visionary province and nation-building projects that support local businesses, secure people’s jobs and strengthen communities,” said Alberta Premier Danielle Smith. “Our economy relies on our highway network and the ability to connect Alberta to markets outside the province.”